Math

If A completes work in 10 days, B in 20 days, together in?

5 days
6.67 days
(Correct)
7 days
8 days
Explanation: Combined rate = 1/10 + 1/20 = 3/20 work/day. Time = 20/3 ≈ 6.67 days.
Latest Job Postings

Assistant (BPS-15)

15 Positions
Gender: Any
Deadline: 14 Sep, 2025
View Details

Junior Clerk (BPS-11)

228 Positions
Gender: Any
Deadline: 08 Sep, 2025
View Details
Explore Mcqs

Urdu

158 Questions

Computer

284 Questions

History

248 Questions